Phase 2 · Module 1 · Backlog & Start

Wk 2 · 90-min workshop + ~3 hrs spread out

🎓 PHASE 2 · MODULE 1
Without a backlog, the loudest voice decides each week; after 5 weeks, 30 instructions are started and none finished. The backlog is your contract document — and your sales tool: when the plant manager asks "what are you actually doing?", you open ONE page.
8–15
entries
1
name per entry
1
page for management
☑️ The workshop — 90 min, 5 steps
Define the area (15 min)
"Packaging line 2" — not "all of production". One line done fully beats five done halfway.
Get 5–8 candidates into the table (30 min)
Per entry: task · use case · today's problem · value. 8 sketched beats 3 perfect.
ONE named person per entry (20 min)
Not "the shift". Plus one backlog lead who keeps the whole thing in view.
Plan how to inform the team (15 min)
5 min per shift, three sentences are enough.
First KPI estimates (10 min)
Baseline → target where measurable. Where not: value in words — invent nothing.
📋 What a backlog looks like — example
CNC-3 · Standard tool change · Mark B. → Setup 30 → 20 min
CNC-3 · Clearing fault E-42 · Mark B. → Downtime −20 min/case
Line 2 · Daily cleaning · Aylin K. → Audit-proof documentation
Goods-in · Labeling variant X · Petra S. → Halve the error rate
Hall A · Forklift visual check · Jorge M. → 100% checks verifiable
☑️ Homework by end of week 2 (~3 hrs)
Sharpen the backlog to 8–15 entries
Measure baselines
Time setups with a stopwatch, ask for scrap rates
Inform all shifts
Start the first 1–2 recordings
Don't wait for a perfect backlog
For module 2: list your 6 stakeholders
⚠️
The 3 killers
  • Ownership assigned to "the team" — then nobody does it.
  • Inviting stakeholders now — too early, they come in module 2.
  • Inventing KPIs — blows up in module 3.
ℹ️
Drill question
Someone says: "I'll take the 5 most important ones and do them all myself." What do you say?